PMP考試模擬試題及答案

字號:

以下是為大家整理的PMP考試模擬試題及答案,僅供參考。
    QUEST Project management provides organizations with a methodology to:
    A Become more efficient and effective in accomplishing goals that cannot be handled well by
    the traditional structure
    B Manage high risk repetitive work
    C Provide clients with multiple points of contact
    D Provide guidance in accomplishing repetitive activities
    E All of the above
    A
    QUEST Configuration (baseline) control monitors performance against the
    A scope baseline
    B original schedule
    C original budget
    D All of the above.
    E None of the above.
    A
    QUEST A summary WBS is usually developed in the
    A Conceptual phase
    B implementation phase
    C planning phase
    D close-out phase
    E All of the above phases
    A
    QUEST A project may be defined as _____
    A an integrated approach to managing projects
    B a coordinated undertaking of interrelated activities.
    C a group of activities directed by a project manger over a life cycle
    D an undertaking with a defined starting point and defined objectives
    E All of the above.
    D
    QUEST Approval to proceed is normally made at the end of the _____ phase of a typical project.
    A conceptual
    B development
    C implementation
    D execution
    E close-out
    A
    QUEST Lessons learned are most often based upon project historical records. Lessons learned can
    be used to:
    A See what mistakes others have made
    B See how others have solved problems
    C Predict trends, highlight problems and identify alternatives
    D All of the above
    E A and B only
    D
    QUEST A program can best be described as:
    A A grouping of related activities which last two years or more
    B The first major subdivision of a project
    C A grouping of projects, similar in nature, which support a product or product line and
    have no definable end point
    D A product line
    E Another name for a project
    C
    QUEST Ensuring that all work is both authorized and funded by contractual documentation is the
    responsibility of:
    A The project manager
    B The functional manager
    C The project sponsor
    D The client
    E All of the above
    A
    QUEST The project charter is a document designed to tell _____ exactly what the project
    entails.
    A The project manager
    B The project office
    C The project team
    D The project sponsor
    E Anyone associated with the project
    E
    QUEST Work authorization forms are needed in order to:
    A Authorize line organizations to charge against the project
    B Establish an audit trail
    C Develop a structured methodology for release of funds
    D All of the above
    E A and C only
    D
    QUEST The scope baseline/project charter is prepared by the:
    A Project manager
    B Project manager and project office
    C Project manager, project office and functional team
    D Project manager, project office, functional team and project sponsor
    E Project manager, project sponsor and customer/user
    E
    QUEST Typical characteristics of a work package include:
    A Representation of units of work at a level where work is performed
    B Clearly distinguishes one work package from all others assigned to a single functional
    group
    C Limits the work to be performed to relatively short periods of time
    D All of the above
    E A and B only
    E
    QUEST Problems can occur in properly defining a project because:
    A Project goals may not be agreeable to all parties
    B The plan was "too loose," thus allowing priorities to change
    C Low turnover of project personnel
    D Too much communication between the client and project personnel
    E The project objectives were quantified
    A
    QUEST In preparing a good project definition, experienced project managers will:
    A Concentrate mainly on the end product rather than costs or benefits. These come later.
    B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must
    get beneath it.
    C Understand that a project definition/plan is a dynamic rather than static tool, and thus
    subject to change.
    D Try to convert objectives into quantifiable terms.
    E All of the above
    E
    QUEST Project life cycles provide a better means of measurement of progress and control. The
    four phases of a project are conceptual development, _____, _____, and _____.
    A Preliminary planning, detail planning, closeout
    B Implementation, reporting, termination
    C Development, implementation, termination
    D Execution, reporting, finishing
    E Implementation, termination, post-audit review
    C
    QUEST The contractual statement of work (CSOW)
    A Must be the same as the proposal statement of work
    B Does not identify reporting requirements
    C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
    D Identifies the contractor’s organizational structure for the project
    E All of the above
    C
    QUEST Which of the following can result in misinterpretation of the statement of work?
    A Using imprecise language (i.e. nearly, approximately)
    B Mixing tasks, specifications, special instructions and approvals
    C No pattern, structure or chronological order
    D Wide variation in the size of tasks or details of work
    E All of the above
    E
    QUEST A project manager believes that modifying the scope of the project may provide added value
    for the customer. The project manager should:
    A Change the scope baseline
    B Prepare a variance report
    C Call a meeting of the configuration control board
    D Change the project’s objectives
    E Postpone the modification until a separate enhancement project is funded after this
    project is completed according to the original baseline
    E
    QUEST The document authorizing functional areas to charge against the project is the:
    A Work authorization form
    B Scope baseline
    C Project charter
    D Management plan
    E Linear responsibility chart
    A