2013年pmp考試模擬題試題及答案

字號:


    項目管理師資格考試頻道為大家整理的模擬試題,供大家學(xué)習(xí)參考。
    QUEST A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be: 
    A 4 weeks 
    B 5 weeks 
    C 6 weeks 
    D 7 weeks 
    E None of the above. 
    B 
    QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to: 
    A All activities. 
    B Only those activities with the longest time durations. 
    C Those activities on the critical path begining with the longest time duration activities. 
    D Those activities with the greatest degree of risk. 
    E None of the above. 
    C 
    QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in: 
    A A shortening of the critical path. 
    B A shortening of the noncritical path. 
    C A decrease in the total cost of the project. 
    D An increase in the cost of the project. 
    E A through D are possible based upon where the resources are deployed. 
    E 
    QUEST Bar charts are most appropriate for: 
    A Comparing actual to planned performance to each activity. 
    B Showing slack time. 
    C Showing critical path dependencies. 
    D Showing which activities can be rearranged in parallel. 
    E All of the above. 
    A 
    QUEST A non-critical path activity is completed in half the time. Then, 
    A The critical path is also reduced. 
    B The slack in the path containing this activity will increase. 
    C The total cost for this activity has decreased. 
    D Manpower from this activity can be assigned to other activities. 
    E All of the above. 
    B 
    QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . 
    A Slack for each activity, critical path. 
    B Slack for each activity, high risk activities. 
    C Manpower shortages, high risk activities. 
    D High risk activities, non-critical paths. 
    E Manpower availability, contingency plans. 
    A 
    QUEST ADM is an activity-on-arrow method. In this method, a dummy activity: 
    A Denotes a critical path relationship. 
    B Denotes any dependency relationship. 
    C Shows slack. 
    D Identifies customer deliverables dates. 
    E Identifies customer team meeting dates. 
    B 
    QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ .
    A Project specification tree. 
    B Customer's deliverable list. 
    C Customer's milestone dates. 
    D Work breakdown structure. 
    E Listing of customer team meeting dates. 
    D 
    QUEST The critical path in a network is the path that: 
    A Has the greatest degree of risk. 
    B Will elongate the project if the activities on this path take longer than anticipated. 
    C Must be completed before all other paths. 
    D All of the above. 
    E A and B only. 
    B 
    QUEST The major difference between PERT and CPM networks is: 
    A PERT requires three time estimates whereas CPM requires one time estimate. 
    B PERT is used for construction projects whereas CPM is used for R & D. 
    C PERT addresses only time whereas CPM also includes cost and resource availability. 
    D PERT requires computer solutions whereas CPM is a manual technique. 
    E PERT is measured in days whereas CPM uses weeks or months. 
    A 
    QUEST A calendar that identifies when a project may be performed on an activity is called a: 
    A Project calendar. 
    B Resource calendar. 
    C Milestone point. 
    D Key point. 
    E Work unit. 
    A 
    QUEST Planning activities such that predetermined resource availability pools are not exceeded is called: 
    A Resource leveling. 
    B Manpower leveling. 
    C Resource limited planning. 
    D Manpower planning. 
    E Manpower contingency planning. 
    C 
    QUEST A comparison of completion status to baseline is referred to as _____. 
    A Earned value measurement. 
    B Percent complete. 
    C ACWP. 
    D BCWS 
    E None of above. 
    A 
    QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as: 
    A Slack 
    B Free float. 
    C Restricted float. 
    D Level float. 
    E Lag 
    E 
    QUEST Overlapping activities on a project, such as design and construction, is referred to as: 
    A Fast tracking 
    B Risk conversion. 
    C Parallel management. 
    D Process improvement. 
    E Synchronous manufacturing 
    A 
    QUEST A computer tape which contains historical project information is called ____ tape. 
    A Database 
    B Baseline. 
    C Archive. 
    D Lessons learned. 
    E Life cycle summary. 
    C 
    QUEST Which method shown below is acceptable for reducing cost or shortening the schedule? 
    A "Crashing" 
    B Changing scope. 
    C Performing activities in parallel rather than in series. 
    D All of the above. 
    E A and C only. 
    D 
    QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. 
    A Increase, decrease. 
    B Increase, increase 
    C Increase, increase or decrease. 
    D Decrease, decrease. 
    E Decrease, increase. 
    B 
    QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____. 
    A Allocation. 
    B Partitioning 
    C Leveling 
    D Quantification. 
    E None of above. 
    A