1. Management decision-making includes:
    A. Analysis of alternatives.
    B. Revisions/replanning.
    C. Resource allocation.
    D. Modification or updating of goals and objectives.
    E. All of the above.
    ANS: E
    2. The basic terminology for networks includes:
    A. Activities, events, manpower, skill levels and slack.
    B. Activities, documentation, events, manpower and skill
    levels.
    C. Slack, activities, events, and time estimates.
    D. Time estimates, slack, sponsorship involvement, and
    activities.
    E. Time estimates, slack time, report writing, life
    cycle phases, and crashing times.
    ANS: C
    3. The project manager must receive reports and
    briefings from engineers, contracting officers,
    procurement personnel and marketing people.
    The project manager’s communication dilemma is one of:
    A. encoding
    B. decoding
    C. choice of a medium
    D. one-way communication
    E. All of the above.
    ANS: E
    4. The technique most commonly used to determine the
    profitability of a project includes _____ methods.
    A. Net present value (NPV).
    B. Return on investment (ROI).
    C. Discounted cash flow (DCF)
    D. Payout time and risk sensitivity analysis.
    E. All of the above.
    ANS: E
    5. Which of the following are part of the purchasing
    cycle:
    A. define need
    B. prepare and issue purchase order
    C. inspect incoming goods
    D. All of the above.
    E. A and B only
    ANS: E
    6. Which of the following is closest to Juran’s
    definition of Quality:
    A. conformance to requirements.
    B. fitness for use.
    C. continuous improvement.
    D. customer focus.
    E. All of the above.
    ANS: B
    7. A project element which lies between two events is
    called:
    A. An activity.
    B. A critical path method.
    C. A slack milestone.
    D. A timing slot.
    E. A calendar completion point.
    ANS: A
    8. Employee unions would most likely satisfy which
    level in Maslow’s hierarchy of needs?
    A. Belonging
    B. Self-actualization
    C. Esteem
    D. Safety
    E. Empowerment
    ANS: A
    9. Management calls a meeting to explain to all
    employees the new benefits package for the rank and
    file. This is an example of:
    A. Upward communication
    B. Downward communication
    C. One-way communication
    D. Two-way communication
    E. None of the above.
    ANS: C
    10. Project management/project planning is most closely
    aligned with:
    A. Long range/strategic planning (5 years or more).
    B. Intermediate range planning (1 to 5 years)
    C. Short range/tactical planning (1 year or less).
    D. All of the above.
    E. B and C.
    ANS: E