ProjectCostManagement

字號(hào):


    Processes required to ensure the project is completed within the approved budget
    Process
     Inputs
     Tools
     Outputs
    Resource Planning
    WBS
    Scope Statement
    Historical Information
    Resource Pool Description
    Organizational Policies
    Expert Judgement
    Alternatives Identification
    Resource Requirements
    Cost Estimating
    WBS
    Resource Requirements
    Resource Rates
    Activity Duration Estimates
    Historical Information
    Chart of Accounts
    Analogous Estimating
    Parametric Modeling
    Bottom-Up Estimating
    Computerized Tools
    Cost Estimates
    Supporting Detail
    Cost Management Plan
    Cost Budgeting
    WBS
    Cost Estimates
    Project Schedule
    Cost Estimating Tools/Techniques
    Cost Baseline
    Cost Control
    Cost Baseline
    Performance Reports
    Change Requests
    Cost Management Plan
    Cost Change Control System
    Performance Measurement
    Additional Planning
    Computerized Tools
    Revised Cost Estimates
    Budget Updates
    Corrective Action
    Lessons Learned
    Estimate At Completion