Qustions 1:
    1. In a weak matrix organization, functional managers are usually responsible for:
    Monitoring personnel performance
    Approval for changes to the project schedule
    Monitoring their project team member’s deliverables
    Changes that impact their team member~ participation
    Qustions 3:
    You are one of four full-time project managers in an organization You all sbare an administrative person There are generally 8-10 projects per year tbat involve about 25% of the organization~enployees, however, these employees do not report to you. Your organization can best be classified as:
    Functional
    Strong matrix
    Projectized
    Balanced matrix
    Qustions 5:
    You have been promoted to Manager, Continuous Process Improvement. Your new position:
    Is a project because the work will be performed by people
    Is not a project because Continuous Process Improvement will continue indefinitely
    Is a project because it is constrained by limited resources
    Is a project because improvements must be plained, executed, and controlled
    Qustions 2:
    As a Project Manager onreplacing2 miles of sewer pipe part of your job is to determine if
    there are cbanges to the scope of the project, the schedule, the budget and the
    tecbnical requirements. These responsibilities are part of wbich process:
    Executing
    Controlling
    Planning
    Closing
    Qustions 4:
    During the course of a project you have motivated team members, managed conflict, performed personnel administrative functions and negotiated for more resources. These are examples of:
    General Management
    Project Human Resource Management
    Project Execution
    A Projectized organization
    Qustions 6:
    Wbich of the following is not a Project Management knowledge area?
    Project Quality Management
    Project Procurement Management
    Project Configuration Management
    Project Risk Management